It’s always fun, starting work on a new milestone. It feels like you’re making huge, absurdly quick progress.
As in this case; after one day of work on MS5, my task tracker tells me that I’m 58% done.
Now, granted, MS5 is by far the shortest milestone I’ve set for myself. I’m aiming to complete it on July 11th; that’s just two weeks away. But still, it would be silly of me to claim that I’m actually “58% done” with this milestone build, since the percentage is calculated based on the number of tasks created, and the number completed.
I tend to add new tasks during the milestone – often my tasks at the start of the milestone include things like “Figure out how to do
In practice, I’m probably closer to 20% of the way done. Which is still pretty good for having spent just one day out of two weeks, so far. Well, two days, since I also worked on Saturday. But you know what I mean.